BOARD
MEETING
August
15, 2002
SUBJECT: MID-CITY/WESTSIDE TRANSIT CORRIDOR WILSHIRE BUS RAPID TRANSIT (BRT) PROJECT
ACTION: APPROVE THE FINAL ENVIRONMENTAL IMPACT REPORT (FEIR) AND AUTHORIZE A PEAK-PERIOD BUS LANE DEMONSTRATION PROJECT
RECOMMENDATION
Certify
the Final Environmental Impact Report (FEIR) for the Mid-City/Westside
Transit Corridor, Wilshire BRT Project;
Adopt
the Findings of Fact and Statement of Overriding Considerations
(Attachment A) and the Mitigation Monitoring Plan (Attachment B);
Authorize
Staff to File a Notice of Determination;
Authorize
a Demonstration and Testing Program for a Dedicated Transit Lane, Subject
to the Approval of Local Jurisdictions (Attachment C).
ISSUE
On
June 28, 2001 the Board approved Bus Rapid Transit (BRT) as the Locally
Preferred Alternative (LPA) for the Mid-City/Westside Transit Corridor-Wilshire
Boulevard route. This action
followed extensive public outreach and review of alternatives contained in the
Draft Environmental Impact Statement/Environmental Impact Report (DEIS/EIR).
The
LPA is defined as a peak-hour dedicated bus lane that would run in the curb
lane of Wilshire Boulevard, subject to the concurrence and approval of local
jurisdictions. Alignments
previously considered that would run in the middle lanes of Wilshire
Boulevard, or would run on a 24-hour basis, were eliminated from further
consideration. The curb lane
configuration is preferred because it eliminates impacts to landscaped
medians, left turn pockets and removes the need for any street widening.
The peak-period only operation is preferred because it allows the
retention of on-street metered parking in most sections of the boulevard.
During
the past year, staff has worked with the City of Los Angeles Department of
Transportation (LADOT) and other affected agencies and jurisdictions to develop
engineering design for the various components of the BRT project.
The components of the BRT project include:
·
Transit Buses – Ninety-seven (97) new 60 foot-long Metro Rapid buses would replace
the existing fleet of 40 foot-long Metro Rapid buses. These buses would feature state-of-the-art, articulated,
low-floor, low-emission vehicle design;
Bus
Transit Shelters-
30 enlarged Metro Rapid bus shelters would be erected at current Metro Rapid
stops between Wilshire/Western and Santa Monica to accommodate 3-door
transit vehicles, universal fare debit card technology, seating, enhanced
lighting and other safety and passenger service features;
Curb
Lane Reconstruction & Repaving – Reconstruction and repaving of the curb
lane and selected intersections between Western Avenue and San Vicente
Boulevard (4 miles) will improve roadway conditions that are presently too
poor to operate advanced transit buses.
In addition, concrete bus pads for longer transit vehicles would be
constructed in West Los Angeles;
Metro
Division #10 Expansion
– Upgrades and expansion to this existing Downtown Los Angeles division
will support the fleet of new articulated transit vehicles;
Parking
Facilities
– Upgrades to Metro owned parking facilities at the Crenshaw and La Brea
Metro Rapid stops will provide parking for transit users and other community
uses;
Peak
Period Lane
– A peak-period (7:00am-9:00am and 4:00pm-7:00pm) dedicated bus lane has
been evaluated in the Final EIR and studied in preliminary engineering
design. The transit lane is
proposed to operate in the curb lane, which is used for parking during most
of the day and as a general-purpose traffic lane in peak periods. Implementation of the peak period bus lane would
therefore not impact on street parking in most segments of the boulevard.
Two segments that are not recommended for implementation of the peak
period lane include the City of Santa Monica segment between Ocean and
Centinela and the Westwood residential segment between Selby and Comstock.
Other segments are recommended, subject to the approval of the local
city or jurisdiction.
The
FEIR evaluates the environmental impacts of the proposed project and provides
responses to more than 5,000 comments received during the Public Comment Period.
The FEIR also identifies mitigation measures that would reduce or
eliminate impacts. Certification of
the Final EIR by the Board is a necessary step to complete the environmental
review of the project and allow the start of final design and construction.
Attachment
A includes the Findings of Fact and Statement of Overriding Considerations.
Attachment B includes the Mitigation Monitoring Plan, which identifies a
number of mitigation measures that would be funded and implemented by the Metro
and others, if the project is implemented.
The California Environmental Quality Act (CEQA) requires approval of
these documents by the Metro, which is acting as lead agency for this project.
Attachment
C provides a Summary of the Wilshire BRT Demonstration Project, which proposes
to test and evaluate a Peak-Period Transit Lane in a segment of Wilshire
Boulevard in West Los Angeles between Centinela and Federal.
Upon approval by the Metro Board, Metro
staff would work with the City of Los Angeles to seek approval to do a trial of
this concept for a period of between 90-180 days, starting in early 2003.
Evaluation and monitoring of the demonstration project would be
conducted, and the results would be reported at the end of the trial period.
This information would be used to help local jurisdictions evaluate the
feasibility of implementing the transit lanes on a permanent basis.
POLICY
IMPLICATIONS
The certification of the FEIR is consistent with the November 1998 Board adopted policy defined in the Regional Transportation Alternatives Analysis (RTAA) and the February 2000 Re-evaluation/Major Investment Study which provide for a Bus Rapid Transit alternative in this corridor. The certification is also consistent with the June 2001 Board approval of the DEIS/EIR Locally Preferred Alternative. The Wilshire BRT Project is included as a component of the Mid-City/Westside Transit Corridor in the Metro Long Range Plan.
OPTIONS
The
Board could defer certification of the FEIR.
However, this action would delay the project schedule, increase cost and
increase the risk of losing funds specifically earmarked for the
Mid-City/Westside Transit Corridor under AB2928.
FINANCIAL IMPACT
Adoption
of the LPA does not have an impact to the Metro FY03 Budget.
The Wilshire BRT costs are within the budget identified in the August 31,
2001 FTA Section 5309 Report. The
current capital cost estimate for the project is $232.2 million in year of
expenditure dollars. Funding is
allocated in Cost Center 4350, project number 800111, task 2.2.10.01 to proceed
with the next step in project development.
This is a multi-year project and the cost center manager and Executive
Officer will be responsible for placing the necessary funds in future year
budgets.
BACKGROUND
Following
the suspension of the Metro Red Line and other Metro rail projects in January
1998, the Board directed the development of the Regional Transit Alternatives
Analysis (RTAA). The RTAA
identified additional cost effective fixed guideway alternatives for the
Eastside, Mid-City/Westside and San Fernando Valley Corridors. In February 2000 the Board adopted the Re-evaluation/Major
Investment Study (MIS) for the Mid-City/Westside Transit Corridor and directed
that environmental clearance proceed for a number of Bus Rapid Transit and Light
Rail Transit alternatives. In June
2001, the Board adopted Bus Rapid Transit (BRT) as the preferred mode for this
alignment and authorized the completion of the final environmental report and
preliminary engineering.
A comprehensive community outreach program was conducted throughout the development of the DEIS/DEIR. The Metro conducted two public scoping workshops and one government agency workshop, in addition to three formal Public Hearings in accordance to Federal and State environmental law. Additionally, a formal public comment period was conducted, which began on April 6, 2001, and extended through June 15, 2001. Over 5,000 comments were received during the public comment period. Most of the comments expressed preferences for or against one or more alternatives studied in the DEIS/DEIR. Several asked technical questions. The comments and responses to each of them are included in Chapter 9 of the FEIR.
The
California Environmental Quality Act (CEQA) Guidelines Section 15091 requires
that the Metro make certain findings with respect to those environmental effects
of the project determined in the EIR to be significant.
These findings are contained in the Findings of Fact and Statement of
Overriding Considerations (Attachment A). In
addition, where significant environmental effects are found not to be avoided or
mitigated to a less than significant level, CEQA requires the Metro must balance,
as applicable, the economic, legal, social, technological and other benefits of
the project against its unavoidable impacts when determining whether to approve
a project. CEQA Guidelines Section
15093(a) states that if the specific economic, legal, social, technological or
other benefits of the project outweigh the unavoidable adverse effects, those
effects may be considered acceptable. The
Metro Board must find that, notwithstanding the disclosure of these significant
and unavoidable impacts, there are specific overriding economic, legal, social,
technological and other reasons, for approving this project and that these
reasons serve to override and outweigh the projects significant unavoidable
effects. Thus, the adverse effects
are considered acceptable. CEQA
requires Metro to support, in writing (Findings and Statement of Overriding
Considerations, Attachment A), the specific reasons for considering a project
acceptable when significant impacts are not avoided or not substantially
lessened.
The FEIR comprehensively responds to all the community comments received during circulation of the DEIS/EIR, which have resulted in mitigation measures are incorporated in the Mitigation Monitoring Plan (Attachment B). The Mitigation Monitoring Plan will be incorporated in the project budget and implemented during construction of the project.
Because of the concern by cities to the effects of the project’s proposed peak period transit lane, a demonstration project is proposed to provide a real world test of the effectiveness of these lanes for improving mobility in the congested Wilshire corridor. Attachment C provides a description of the proposed Wilshire BRT Peak Period Transit Lane Demonstration Project. This demonstration would only be undertaken if supported by the City of Los Angeles. The City of Los Angeles Department of Transportation has reviewed proposed plans for this demonstration project and would work with Metro staff to implement the test project if directed to do so by the City Council.
NEXT
STEPS
Assuming
Board certification of the FEIR, adoption of the LPA, as well as adoption of the
Mitigation Monitoring Plan and the Findings of Fact and Statement of Overriding
Considerations, Metro staff and consultants will proceed with preparation of
contract documents and solicitation efforts for procurement of the Wilshire BRT
project components. A total of 6
different construction and/or third party agreements are envisioned:
Curb
Lane Reconstruction & Repair (Western to San Vicente) plus Bus Pad
Construction in West Los Angeles (Centinela to Westwood)
Vehicle
Procurement (Incorporated into Advanced Technology Bus Procurement)
Bus
Shelter Agreement with Cities for Implementation and Maintenance
Division
#10 Acquisition, Design and Construction
Crenshaw
and La Brea Parking Facility Upgrades
Demonstration
Lane Implementation and Testing
ATTACHMENTS:
A
Findings of Fact and Statement of Overriding
Considerations
C
Summary
of Wilshire BRT Peak Period Transit Lane Demonstration Project
Prepared by: David Mieger, Director
Westside Area
Planning Team
|
JAMES
L. de la LOZA Executive
Officer Countywide
Planning and Development |
|
ROGER
SNOBLE Chief
Executive Officer |