MINUTES/PROCEEDINGS
LOS ANGELES COUNTY
METROPOLITAN TRANSPORTATION AUTHORITY
REGULAR BOARD MEETING
BOARD OF DIRECTORS
Metro Headquarters - 3rd Floor, Board Room
One Gateway Plaza, Los Angeles
December 2, 1999
Called to order at 10:00 A.M.
Directors Present:
Yvonne Brathwaite Burke, Chair
James Cragin, First Vice Chair
Richard Riordan, Second Vice Chair
Hal Bernson
Jaime de la Vega
John Fasana
Don Knabe
Jose Legaspi
Gloria Molina
Jenny Oropeza
Frank Roberts
Zev Yaroslavsky
Robert Sassaman, Ex Officio
Chief Executive Officer - Julian Burke
Board Secretary - Michele Jackson
Inspector General - Arthur Sinai
General Counsel - County Counsel
NOTE:
Members voting are reflected on the attached
“RECAP OF PROCEEDINGS” matrix.
1.
APPROVED CONSENT CALENDAR Items 2, 9, 10, 17, 18, 26, 29, 30, 34, 35, 40,
48***, 50,
51, 53,
55, 56, and 57
ITEMS 8*** AND 45 WERE PULLED FROM CONSENT
*** 2/3 VOTE REQUIRED BY THE FULL BOARD
NOTED COMMITTEE
AUTHORITY ITEMS: 11, 12, 13, 15,
16, 19, 20, 21, 22, 23, 43, 44, 46,
and 47
CONSENT
CALENDAR
2.
APPROVED ON CONSENT CALENDAR Minutes of Special Board Meeting held on
September
29, 1999 and
Regular Board Meeting held on October 28, 1999.
9. APPROVED ON CONSENT
CALENDAR award of a firm fixed unit price contract to Trans Glass Inc., the only
responsive, responsible bidder under Bid #09-9913 to purchase up to 222 TMC, 148
Neoplan and 19 GMC RTS Window Kit Assemblies, for an amount not to exceed
$2,488,355, inclusive of sales taxes.
10. APPROVED ON CONSENT CALENDAR
appointment of a Hearing Officer and scheduling of a Public Hearing for Tuesday,
January 18, 2000 at 10:00 a.m., to receive public comments regarding the
proposal from Montebello Bus Lines to operate Line 104.
17. APPROVED ON CONSENT CALENDAR execution of Change Order No. 138 to Contract C0351, North Hollywood Station with Crossover and Tail Track, with Kajima/Ray Wilson, J. V., to closeout temporary decking for the station box and station side structures for actual quantities installed, on the Metro Red Line, North Hollywood Extension, in the amount of $522,500 increasing the total contract value from $67,860,244 to $68,382,744.
18. APPROVED ON CONSENT CALENDAR
execution of Change Order No. 112.00 to Contract No. C0351, North Hollywood
Station with Crossover and Tail Track with Kajima/Ray Wilson, J. V.,
to add concrete sealer in the amount of $49,019 and to delete acoustical
material within the station in the credit amount of ($284,310) on the Metro Red Line, North Hollywood Extension for a net credit amount of ($235,291),
decreasing the total contract value from $67,860,244 to $67,624,953.
26. ADOPTED ON CONSENT CALENDAR two separate resolutions, one for Prop A and one for Prop C, required by the State Board of Equalization (SBOE) AND AUTHORIZED Metro staff and Municipal Resource Consultants to audit SBOE sales and use tax records.
29. APPROVED ON CONSENT CALENDAR
adoption of the updated Metro Debt
Policy.
30. APPROVED ON CONSENT CALENDAR
exercising the second one-year option at the same monthly fee for state advocacy
support:
A.
Capitol Representation Group - $71,500.
Tim Egan principal lobbyist.
B.
Nielsen, Merksamer, Parrinello & Naylor - $57,130.
Bob Naylor principal lobbyist.
34. APPROVED ON CONSENT CALENDAR
adoption of the 1999 Congestion Management Program for Los Angeles County.
35. APPROVED ON CONSENT CALENDAR a request from Caltrans for an increase of $535,000 in the expenditure limit for the construction contract for the I-405 HOV project, awarded by Caltrans to Brutoco Engineering and Construction, Incorporated (Contract #07-120334), needed to settle the contractor's final claims filed for additional cost items. The new expenditure limit will be $14,203,000 which is less than the $14,801,000 in federal and state Transportation Systems Management (TSM) Matching funds that were originally programmed by the Board as part of the 1993-94 Metro Call for Projects.
40. APPROVED ON CONSENT CALENDAR:
A. execution of a contract with TM TechSystems to provide consulting and technical support services related to the Advanced Transportation Management System (ATMS) project for a period not to exceed five years for a firm fixed price amount of $1,355,000; and
B.
negotiation and execution of additional Task Orders up to 15% of the original approved contract value, as a not to exceed
contingency of $203,000, for a total contract value of $1,558,000.
48. APPROVED ON CONSENT CALENDAR BY A 2/3
VOTE:
A.
Adoption of the following motion: The
Board finds by a two-thirds vote that awarding a design/build contract pursuant
to Public Utilities Code 130242(a) will achieve certain private sector
efficiencies in the integration of the design and construction of the Metro
Green Line (D Line) Noise Barrier; and
B.
Authorization for the CEO to solicit design/build Contract C0637, Metro
Green Line (D Line) Noise Barrier, pursuant to Public Utilities Code 130242(a).
50. APPROVED ON CONSENT CALENDAR
declaring real property located at 9920 Flora Vista Street in the City of
Bellflower as surplus and authorized the sale of said property to the City of
Bellflower for $1,050,000.
51. APPROVED ON CONSENT CALENDAR
negotiation and execution of a
sublease agreement with Prism Communication Services, Inc., a wholly
owned subsidiary of Comdisco, Inc., for the sublease of approximately 17,978
square feet of office space at 707 Wilshire Boulevard, Los Angeles, for a flat,
full-service-gross, monthly rental rate of $14,982 per month ($0.83 per square foot) over the sublease term,
with four months of free rent and use of existing furniture.
The term of the sublease agreement shall commence on approximately
December 15, 1999 and run for the then remaining twenty-five-and-one-half month
term on the Metro's 707 Building lease.
53.
APPROVED ON CONSENT CALENDAR authorization for the Chief Executive
Officer to exercise the second one-year renewal option with each Certified
Public Accountant (CPA) firm within the CPA Audit Pool for services from
December 2, 1999 through December 1, 2000 in
an aggregate amount not to exceed $3,345,000, increasing the total amount
authorized from $3,279,107 to $6,624,107.
55. APPROVED ON CONSENT CALENDAR
Yaroslavsky motion - that staff report back to the Board
in 30 days with a financing and operational plan to immediately extend
rail hours to serve the Staples Center and Music Center;
That staff should work with Staples Center, Music Center and LADOT staff to ensure that the expanded service is sufficient to meet ridership demands; and
That staff should report back to the Board in 60 days with a cost and operational plan for extending rail hours and service in the spring when Red Line opens to North Hollywood. Staff should work with all interested parties including Universal Studios, the Universal Amphitheater, Hollywood Bowl, Trizec Hahn and other interested parties.
56. APPROVED ON CONSENT CALENDAR
execution of an amendment to Contract No. 07H004 with MK Centennial to provide
design services for Route 10 HOV Lanes, Segment 3 project from Route 57 to the
San Bernardino County Line in the amount of
$505,436 for a total revised contract amount of $9,015,436.
57. APPROVED ON CONSENT CALENDAR
Riordan motion to:
1. Begin free Metro bus and rail
service at 11 a.m. on December 31, 1999;
2. Monitor actual Metro fare
revenue on December 31, 1999 versus the expected
revenue;
3. Transfer sufficient funds up to
$250,000 from the Board Contingency to Metro transit
operations if Metro
fare revenue is less than projected revenue for December 31, 1999;
4. Report back to the Board during
the January, 2000 committee cycle with the actual cost
of extending
transit service.
APPROVED
UNDER COMMITTEE AUTHORITY
Items 11, 12, 13, 15, 16, 19, 20, 21, 22,
23, 43, 44, 46 and 47
11. APPROVED UNDER OPERATIONS
COMMITTEE AUTHORITY negotiation and execution of a five (5) year firm fixed
price contract to The Resource Collection, Inc., for janitorial services for
Harbor Transit Way Stations and Customer Service Centers, at a total contract
value of $583,961, inclusive of two (2) one-year options.
12. APPROVED UNDER OPERATIONS
COMMITTEE AUTHORITY:
A.
award of a firm fixed price contract to N/S Corporation, Inglewood, the
lowest responsive, responsible bidder, for two Bus Washing Systems to be located
at Divisions 3, and 5, for a firm fixed price of $344,250; and
B. exercise of a
contract option for two additional bus washing systems for a price of $344,250,
for a total contract value of $688,500.
13. APPROVED UNDER OPERATIONS
COMMITTEE AUTHORITY award of a 36-month unit rate contract to Electric Motors
Sales and Service, Alhambra, the lowest responsive, responsible bidder to
overhaul Metro Blue Line, Metro Green Line (D Line) and Metro Red Line Traction Motors
for an amount not to exceed $630,963.
15.
APPROVED UNDER CONSTRUCTION COMMITTEE AUTHORITY execution of Change Order
No. 6.00 to Contract B612 with L. B. Foster Company for deletion of the Contact
Rail System for Metro Red Line Segment 3 Mid-City, Stage 2(b) rail extension and
the Eastside Extension option, in the credit amount of ($1,169,166), decreasing
the total contract value from $9,492,567 to $8,323,401.
16. APPROVED UNDER CONSTRUCTION
COMMITTEE AUTHORITY execution of Change
Order No. 7 to Contract No. C1610 Trackwork Installation, with Herzog
Contracting Corporation to delete the Crossover Trackwork Installation on the
Metro Red Line North Hollywood Extension, in the credit amount of ($289,000),
decreasing the total contract value from $26,448,789 to $26,159,789.
19. APPROVED UNDER CONSTRUCTION
COMMITTEE AUTHORITY execution of Change Order No. 109 to Contract C0321,
Universal City Station, with Tutor-Saliba/Perini, J. V., to close out
Exterior Wall Concrete for the actual quantities installed on the Metro
Red Line, North Hollywood Extension, in the credit amount of ($243,380),
decreasing the total contract value from $60,951,947 to $60,708,567.
20. APPROVED UNDER CONSTRUCTION
COMMITTEE AUTHORITY execution of Change Order No. 196 to Contract No. C0301,
Hollywood/Highland Station and Tunnels, with Tutor-Saliba/Perini, J. V., to
delete Chiller Room on the Metro Red Line, North Hollywood Extension, in the
credit amount of ($273, 478), decreasing the total contract value from
$75,493,504 to $75,220,026.
21. APPROVED UNDER CONSTRUCTION
COMMITTEE AUTHORITY execution of Change Order No. 68.00 to Contract B252,
Vermont/Santa Monica Station and Crossover, with Kiewit-Shea, J. V., to close
out Concrete Reinforcing Steel for actual quantities installed on the Metro Red Line, Vermont/Hollywood Corridor, in the amount of $676,337 increasing the total
contract value from $56,000,530 to $56,676,867.
22. APPROVED UNDER CONSTRUCTION
COMMITTEE AUTHORITY:
A.
award of a Time and Materials Contract Work Order type contract to
Harding Lawson Associates to provide the Metro environmental engineering services
for two (2) years with three (3) one year options; and
B.
negotiation and execution of Contract Work Orders for environmental
engineering services in an amount not to exceed $3,037,493.
23. APPROVED UNDER CONSTRUCTION
COMMITTEE AUTHORITY execution of Change Order No. 16 to Contract No.
OP33430312-A with Funds Management, Inc. to provide compensation for additional
shoring required due to unforeseen site conditions on the underground storage
tank replacement at Division 15 in the amount of $136,345, increasing the total
contract value from $1,861,682 to $1,998,027.
43. APPROVED UNDER CONSTRUCTION
COMMITTEE AUTHORITY execution of Change Order No. 16 to Contract No. C1610
Trackwork Installation, with Herzog Contracting Corporation, to modify the
Contractor's Rail Welding Site and Construction Staging Area on the Metro Red Line North Hollywood Extension, in the credit amount of ($241,000), decreasing
the total contract value from $26,159,789 to $25,918,789.
44. APPROVED UNDER CONSTRUCTION
COMMITTEE AUTHORITY:
A.
execution of Work
Authorization Change Notice (WACN) No. 20.02 to Contract No. H0631, Traction
Power Installation, with MASS
Electric Construction Co., for the completion of the installation of additional
upgrade equipment to Segment 1 Traction Power System on the Metro Red Line,
North Hollywood Extension. This
WACN 20.02 supercedes WACN 20.01 which was issued within staff authority to
begin the installation effort and increases WACN 20.01 from $195,000 to
$608,245, increasing the total contract value from $3,855,255 to $4,463,500;
B.
negotiation and execution of Change Order No. 5.00 within the not to
exceed amount approved by this WACN;
C.
an increase in the Authorization for Expenditure (AFE) to Contract No.
H0631 to provide funding in the amount of $608,245 increasing the current
contract AFE amount from $4,579,539
to $5,187,784.
46. APPROVED UNDER CONSTRUCTION
COMMITTEE AUTHORITY award of Cost-Plus-Fixed Fee (CPFF) Contract No. PS
8310-0566 with Systra Consulting, Inc. for design and design support during
construction services for the train control systems and associated interfaces on
the Metro Green Line (D Line) and Metro Blue Line light rail transit systems from July 1,
1999 through September 30, 2001 in an amount not to exceed $1,454,403.
47. APPROVED UNDER CONSTRUCTION
COMMITTEE AUTHORITY authorization for the CEO to execute the following contract
work orders (CWO) to contract ENO30
with CH2MHILL (Santa Ana) on the Metro Red Line East Side Extension for asbestos and lead abatement
for a total aggregate increase in the current CWO value of $307,956 from $35,896 to $343,852:
A.
Contract Work
Order (CWO) No. 24.1 of Parcel ED-147, in the amount of $197,971;
B.
CWO No. 25.1, Parcel EE-279 in the amount of $41,843;
C.
CWO No. 28.1, Parcel EE-283, in the amount of $68,142;
and
D.
increase the Authorization for Expenditure (AFE) to provide funding for
pending changes that are within the Board delegated authority in the amount of
$75,000 ($45,00 for asbestos and lead abatement of buildings on Parcels
ED-147,EE-279, and EE-283; and $30,00 for Environmental Emergency Response
services) increasing the current AFE amount from $300,000 to $375,000.
NON-CONSENT
3.
Chief Executive Officer's Report
· CNG Fueling Facility At Division 5
· Transit Corridor Studies for Alternative Fixed Guideways
· UFS/ETM Special Board Meeting December 15, 1999 at 1:00 p.m.
· Compton Metro Blue Line Accident
4. Chair's Report
APPROVED Burke Motion, as Amended by Bernson:
THAT the Board direct staff to report back to the
Operations Committee in 60 days on the following issues:
1.
The status of the Metro’s current Metro Blue Line safety programs including
publicity and awareness education;
2.
A review of
other rail properties’ experiences & solutions relating to similar
at-grade light rail safety issues;
3.
Possible
additional efforts to effectively boost safety, including but not limited to
additional safety education programs, and design improvements, such as median
islands, four quadrant gates, separate left-turn phases, and other alternatives,
including all possibilities surrounding grade separations;
4.
Levels of
funding required to implement the above range of improvements;
5.
Identify any
legislative efforts needed to secure appropriate funding for improvements or
other enhancements of Metro’s Rail Safety Program; and
6. look at proposing legislation that would make it a criminal act (misdemeanor) to ignore traffic laws and safety systems.
5. APPROVED ‘A’ ONLY
CRAGIN MOTION:
A.
that no change be made to the formula for allocation of Federal Section
5307 or in the way these funds are allocated, and that Metro's FY 2000 and FY 2001
budgets reflect that policy position;
B.
CARRIED OVER FOR 60 DAYS AND DIRECTED THE CEO TO CONTINUE TO WORK WITH
THE MUNICIPAL OPERATORS
regarding creation of a Municipal Operator Bus Service improvement and expansion
program designed to improve service to the transit dependent countywide by
reducing overcrowding and expanding services; and that the Board authorize the
CEO or his designee to execute funding agreements with the Municipal Operators;
and that those agreements provide a total for Municipal Operators, for this
program, of proposition C 40% funds of $5 million for FY2000;
a minimum of $10 million for FY 2001; and a minimum of $15 million each
for FY's 2002, 2003 and 2004; Recognizing
that these sums are much less than the estimated fair share the municipal
operators should receive based on anticipated funding Metro will need.
8. ADOPTED BY 2/3 VOTE
OF THE BOARD THE FOLLOWING MOTION:
A.
That there is only a single source of procurement for five hundred fifty
(550) bicycle racks and assist mirrors and purchase is for the sole purpose of
duplicating the bicycle racks and assist mirrors already in use.
The Board hereby authorizes the purchase of the bicycle racks and assist mirrors under PUC Section
130237; and
B.
Awarded a firm fixed price contract to Sportworks NW, Inc. Woodinville,
Washington, for the procurement of 550 bicycle racks and 550 assist mirrors for
the Metro Bus fleet, at a total contract value of $291,407, including sales tax.
31. APPROVED, AS AMENDED:
Adoption of the proposed 1999-2000 Legislative
Program - Second Session AMENDED TO INCLUDE:
SEEKING FUNDING FOR RESEARCH AND DEVELOPMENT OF THE
CNG ENGINE.
SEEKING A LETTER OF NO PREJUDICE FROM THE FTA RELATED
TO THE THREE CORRIDORS (ALAMEDA CORRIDOR EAST, MID-CITIES AND SAN FERNANDO).
EXPAND THE 1999-2000 STATE PROGRAM
- PROPOSED ACTIVITIES TO INCLUDE:
EFFORTS TO SECURE ADDITIONAL FUNDING AND/OR OBTAIN
AUTHORITY TO GENERATE ADDITIONAL FUNDING FOR BUS TRANSIT CAPITAL, OPERATIONS,
THE POST 1989 SOUNDWALL LIST, AND ANY
OTHER PROJECTS, PROGRAMS AND SERVICES BENEFICIAL TO LOS ANGELES COUNTY.
EXPAND THE 1999 REGIONAL AND LOCAL PROGRAM TO
INCLUDE:
SUPPORTING THE PROGRESS OF THE ALAMEDA CORRIDOR AND
ALAMEDA CORRIDOR EAST.
MITIGATE THE IMPACT OF HOV LANE CHANGES ON Metro BUS
SERVICE.
32. APPROVED:
MOLINA/ANTONOVICH MOTION that Section 1.4E of the Metro
Rules and Procedures be amended to read as follows:
Committee actions.
All actions taken by a committee, other than actions requiring a 4/5
vote, shall require the affirmative vote of a majority of all appointed
committee members. All actions
taken by a committee which require a 4/5 vote for approval shall require the
affirmative vote of 4/5 of all appointed committee members.
Any agenda item which does not receive a sufficient
vote for approval as required by this section shall be forwarded to the full
board for consideration without recommendation by the committee.
33. CLOSED SESSION
A.
Conference with Legal Counsel - Existing Litigation - G.C. 54956.9 (a):
1. Birdsong v. Metro
Case No. BC205177
APPROVED SETTLEMENT OFFER in the amount of $225,000
2.
Labor/Community Strategy Center v. Metro, Case
CV 94-5936TJH
NO
ACTION TAKEN
3.
Bachman v. Metro BC198819
APPROVED SETTLEMENT in the amount of $150,000
4. Anguiano v. Metro, Case BC
196000
APPROVED SETTLEMENT in the amount of $295,000
5. Metro v.
Parsons/Dillingham Case BC 150298
NO ACTION TAKEN
B. Closed Session: Conference
with Legal Counsel - Anticipated Litigation
1.
G.C. 54956.9 (b)
Significant
exposure to litigation (One Case)
APPROVED SETTLEMENT of $195,000 for 6150 Hollywood
Blvd. property
2.
G.C. 54956.9 (c)
Initiation
of litigation (One case)
AUTHORIZED ACCEPTANCE OF $320,000 OFFER from Southern California Gas
Company
42. APPROVED
execution of a revision to Work Authorization Change Notice (WACN) No. 469 to
Contract No. 3369 with Parsons-Dillingham (P-D) to fund the cost of four months
of Construction Management Services on the Metro Red Line, Vermont/Hollywood
Corridor (Segment 2B) in an amount not to exceed $1,500,000, increasing the WACN
amount from $1,500,000 to $3,000,000, and increasing the total contract value
from $173,781,912 to $175,281,912.
45. APPROVED RIORDAN/YAROSLAVSKY
SUBSTITUTE MOTION TO:
A.
authorize the CEO to negotiate and execute change orders to Contract No.
PM021 with Fluor Daniel Inc., for Project Management Assistance (PMA) services
for North Hollywood, Segment 3 ($83,000) and LA Car Activation Support ($66,000)
in the amount of $149,000 increasing the total contract value from $16,120,000
to $16,269,000;
B.
increase
the Authorization for Expenditure (AFE) to Contract No. PM021 to provide funding
for pending changes increasing the current contract AFE by $149,000 from
$16,120,000 to $16,269,000; and
C.
direct
the CEO to move forward to pre-qualify and negotiate a sole source contract at a
lower rate with PinnacleOne.
58. WITHDRAWN - ANTONOVICH MOTION
that the Board transmit a letter of support to the FHWA for the $35 million
Montebello Blvd., grade separation project.
RECEIVED PUBLIC COMMENT
Chair Burke requested a report back on the LA Car.
PREPARED
BY: Rhodona Enright
Recording Secretary
Michele Jackson
Board Secretary